Ongoing Projects

Projects under Construction:

North-South Corridor is one of the main projects of Program Management Office    which is 238.9 km and constitutes three packages. First package within this project is Mazar-e –Shrif –Pule Baraq is completed but 2 anothr projects (Pule Baraq – Dar-i-Suf & Bamyan – Yakawlang) under construction which is showing below:

1. Mazar-e-Sharif – DaraSoof (140 km): The work of this project started in November 2007 and is still under construction. The project will be completed in November 2011.

2. Bamian – Yakawlang (50 km): This project started in November 2007 and is still under construction. The work of the project will be completed in May 2011.

3. Bagrami – Separi (50 km): This project started in August 2010 and is still under construction. The work of the project will be completed in August 2013.

4. Jabul Saraj – Nijrab (50 km): The work of this project started in August 2010 and is still under construction. The work of the project will be completed in August 2012.

5:Pule Baraq – Dari Suf is the second package within this project. The length of the road for this package is 64.5km. This contract was awarded on 1/11/2007 to SAMWHAN Corporation. The total amount of this project is 44.55 million dollars. The construction works of this project commenced on 8/5/2008 and the expected completion date of this package is 4/11/2011 and progress of the physical work up to end of June 48.95% and disbursement to contractor was $22.24 million Based security problem civil work in that project was stopped from 17Dec 2010, but           As per the Contractor information the Security Situation is getting better and profitable for execution of the project.

6:Bamyan – Yakawlang is the third package within this project. The length of the road for this package is 98.9km. This contract was awarded on 1/11/2007 to SAMWHAN Corporation. The total amount of this project is 69.11 million dollars. The construction works of this project commenced on 8/5/2008 and the expected completion date of this package is 4/11/2011the project is ongoing, but duty some LARP problem and design aletetions just time extention is awarded to be completed in 30 June 2012 and progress of the physical work up to end of November 87.77% and disbursement to contractor was $53.18 million. The Land Acquisition and Resettlement Plan (LARP) for these three packages have already been completed and all the required documents have been submitted to Cabinet approval.

7:Bagramy – Sapary is another project with the length of 50km. The contract is awarded on 29/5/2010 to Heim-German. The construction works of this project commenced on 26/8/2010 and the expected completion date of this project is 25/8/2013. The total amount of this project is 50.517341 million dollars and progress of the physical work up to end of November 19.4% and disbursement to contractor was $12.51 million.

Projects under Procurement:

1:Faizabad – Baharak (44 km): This project is still under procurement.

2:Qaisar – Leman (233 km): This project is still under procurement.

3:Lashkarga – Chah-e-Angeer The length of this project is 31.6km. This project under procurement procedure.