REMABAR II Rehabilitation Works on the Section 2 of the Maidan Shar – Bamyan Road, from Bamyan to Onay Pass

REMABAR II

Rehabilitation Works on the Section 2 of the Maidan Shar – Bamyan Road, from Bamyan to Onay Pass

 

  1. EMABAR I -  54 km from Maidan Shar to Onai pass, completed in 2011 with a grant worth Euro 36 million from the Italian Government; and
  2. REMABAR II -  82 km from Bamyan to Onai Pass is ongoing according to the plan, and includes construction works such as bridges with different spans, pipe and box culverts, filling, cutting, excavations and asphalting of the road.
  3. Totally the physical progress percentage from km 54+000 to km 136+200 has reached more than 80%. Out of the 82 km road, 30 km has been asphalted; 15 bridges with spans of 10 to 40 meters have been constructed and more than 350 pipe and box culverts have been constructed.
  4. There are some security problems along the road from Maidan Wardak to Onay Pass.
  5. Expected date for completion of the construction works is late 2015.