Kandahar: 2nd lot of SpinBoldak highway reaches to 70% work progress

Anonymous (not verified)
Tue, Mar 30 2021 10:42 AM
Kandahar: construction of 2nd lot of SpinBoldak highway reaches 70% progress

The construction of the road between Kandahar City and SpinBoldak district, which is more than 39km-long and 11.2m-wide, has reached 70% progress to be completed.

According to the Ministry of Public Works, the under-construction portion is the supplementary part of the Kandahar-SpinBoldak regional highway project, which is funded from the national budget of Afghanistan’s Government.

The project is including the construction of two bridges with lengths of 24 and 180 meters each, 66 culverts, 7 crossings points, and shoulders improvement both-sides of the road.

MoPW says the overall completion of the project will have a significant impact to connect remote areas, improve living conditions, and will strengthen-up the regional transit connectivity between Afghanistan and Pakistan.

MoPW Media Team - Kabul

.

1 year 6 months ago

.

تازه ترین اخبار

Tue, Jul 27 2021 1:35 PM
Background image

Maintenance of 6.98 km part of Kabul-Kandahar highway completed

Zabul: Ministry of Public Works announced the periodic maintenance and rebuilding of a 6.98-kilometer long road in the Shajoi district of Zabul province, which is a part of the Kabul. . .

Tue, Jul 27 2021 1:09 PM
Background image

Daikundi: The urban roads of Nili City reach 73% progress

The 8.8 km long and 14 meters wide urban roads project in Nili city, the capital of Daikundi province, is underway and has reached 73% of physical progress, so far.

According to the. . .

BACK TO NEWS