Paktia: Construction of 4.5 km of road in Sidak Karam district hits 60% progress

Anonymous (not verified)
Sun, Jul 04 2021 4:36 PM
Paktia: Construction of 4.5 km of road in Sidak Karam district hits 60% progress

Construction of a 4.5 km long concrete road with its belonging structures in Muchalgho village of Sayed Karam district of Paktia province, has reached 60% physical work progress so far.

The project has been contracted between the Ministry of Public Works and four local development councils and is funded by the Government of Afghanistan.

During this project, some 20,415 working days have been created directly and indirectly for a number of local residents, and with the completion of this project, the villages of Gwad Mangal, Haji Aziz, Miyadad, Karaki Khel, and Muchalgho will be directly connected with Gardez-Seyed Karam main district road.

MoPW Media Team – Kabul

.

11 months 2 weeks ago

.

Latest news

Tue, Jul 27 2021 1:35 PM
Background image

Maintenance of 6.98 km part of Kabul-Kandahar highway completed

Zabul: Ministry of Public Works announced the periodic maintenance and rebuilding of a 6.98-kilometer long road in the Shajoi district of Zabul province, which is a part of the Kabul. . .

Tue, Jul 27 2021 1:09 PM
Background image

Daikundi: The urban roads of Nili City reach 73% progress

The 8.8 km long and 14 meters wide urban roads project in Nili city, the capital of Daikundi province, is underway and has reached 73% of physical progress, so far.

According to the. . .

BACK TO NEWS