Parwan: Thop Dara - Khwaja Sayaran road has 67% progress

ناپیژنده (not verified)
چهارشنبه ۱۴۰۰/۴/۹ - ۱۴:۱۶
Parwan: Thop Dara - Khwaja Sayaran road has 67% progress

This asphalt road, from the Thop Dara to Khwaja Sayaran Ulya and Sufian Bala, has a length of 4.49 km and Its construction work continues with 67% progress, so far.

The project is contracted between the Ministry of Public Works and a private company and is funded by the Government of Afghanistan.

During the construction of this road, some 2100 working days have been provided for a number of local residents.

With the completion of this project, at least five villages will be connected with each other, and the regional people will get more close to their designated destinations.

MoPW Media Team – Kabul

...

8 میاشتې 2 اونی ago

...

تازه خبرونه

شنبه ۱۴۰۵/۲/۱۹ - ۱۰:۵۵
Background image

په بلخ ولایت کې د بلخ – شبرغان لارې د لومړي لاټ (د کلفت بندر سړک) رغنیزې چارې روانې دي

د بلخ شبرغان لارې لومړی لاټ (د کلفت بندر سړک)، ۲۵ کیلومتره اوږدوالی لري، چې د څه باندې ۷۵۲ میلیونه افغانیو په ارزښت، د ټولګټو وزارت او د سړک جوړونې له یو خصوصي شرکت سره د ډیزاین بیل. . .

چهارشنبه ۱۴۰۵/۲/۱۶ - ۱۳:۲۶
Background image

د ا.ا.ا د ټولګټو وزارت وزیر د ایران اسلامي جمهوریت له سفیر سره وکتل

د ا.ا.ا د ټولګټو وزارت وزیر محترم الحاج ملا محمدعیسی ثاني د ایران اسلامي جمهوریت له سفیر ښاغلي علیرضا بیکدلي سره په خپل کاري دفتر کې په داسې حال کې وکتل چې د ټولګټو وزارت تخنیکي مرستیال. . .

چهارشنبه ۱۴۰۵/۲/۱۶ - ۱۱:۲۰
Background image

په تېره اوونۍ کې د اوسپنې پټلۍ له لارې ۲۲۹۵۳۶ مټریک ټنه انتقالات شوي دي

په تېره  اوونۍ کې (د ۱۴۰۵ هـ.ش. کال د ثور له ۴مې نېټې څخه  تر ۱۰مې) نېټې پورې د ټولګټو وزارت د اوسپنې پټلۍ له لارې  ۲۲۹۵۳۶ مټریک ټنه انتقالات شوي دي.

د حیرتان بندر له لارې ۱۵۸۱۳۳ټنه، د. . .

BACK TO NEWS