Daikundi: The entire roads of Nili city hits 70% progress

ناپیژنده (not verified)
پنجشنبه ۱۴۰۰/۳/۱۳ - ۱۱:۵۹
Daikundi: The entire roads of Nili city hits 70% progress

The 8.8 km long and 14 meters wide urban roads project in Nili city, the capital of Daikundi province, is underway and reached 70% of physical progress.

According to the Ministry of Public Works, the contract of this project was signed with a private construction company, which valued more than 631 million Afghanis and funded by the Afghan government.

The implementation of this project was the main demand of the people of Daikundi province. With the completion of this project, in addition to reducing traffic congestion and air pollution inside the city; indeed, it will also reduce the transport costs and waste of time.

MoPW Media Team - Kabul

...

4 میاشتې 3 اونی ago

...

تازه خبرونه

یکشنبه ۱۴۰۴/۱۰/۲۸ - ۹:۳۵
Background image

د کابل – جلال آباد لویې لارې د دویم لین سړک له رغنیزو چارو څخه د ټولګټو وزارت د محترم وزیر لیدنه

د ا.ا.ا د ټولګټو وزارت محترم وزیر الحاج ملا محمد عیسی ثاني، چې د یاد وزارت یو شمېر تخنیکي رئیسانو یې ملتیا کوله پرون د جمعې په ورځ د کابل – جلال آباد لویې لارې د دویم لین سړک د ۳۲. . .

پنجشنبه ۱۴۰۴/۱۰/۲۵ - ۹:۴۴
Background image

د شاه ولي کوټ – ترینکوټ ۲۴ کیلومتره سړک رغنیزې چارې جریان لري

د ا.ا.ا د ټولګټو وزارت له لوري د شاه ولي کوټ – ترینکوټ د عمومي مسیر د ۲۴ کیلومتره برخې د اساسي رغونې چارې د شاوخوا ۷۹۲ میلیونه افغانیو په ارزښت روانې دي.

یاد سړک د کندهار ولایت له ټغرک. . .

یکشنبه ۱۴۰۴/۱۰/۲۱ - ۱۳:۴۰
Background image

په تېره اوونۍ کې د اوسپنې پټلۍ له لارې (۱۵۷۹۹۹) مټریک ټنه انتقالات شوي دي

په تېره  اوونۍ کې (د ۱۴۰۴ هـ.ش. کال د جدي له ۱۲مې څخه تر ۱۸مې) نېټې پورې د ټولګټو وزارت د اوسپنې پټلۍ له لارې (۱۵۷۹۹۹) مټریک ټنه انتقالات شوي دي.

د حیرتان بندر له لارې (۱۰۶۹۸۴) ټنه، د. . .

BACK TO NEWS