Najrab district’s road construction reaches 24% physical progress

Anonymous (not verified)
سه‌شنبه ۱۴۰۰/۴/۱ - ۱۵:۱۷
Najrab district’s road construction reaches 24% physical progress

Kapisa: The construction of the road in the Najrab district of Kapisa province in four sections (Hood, Jorghal, Kharaj, and Ghacholan) is under construction by the Ministry of Public Works.

According to the Ministry of Public Works, the construction works of this project have 24.5 percent progress so far.

This road is more than 15 kilometers long and 6.6 m wide, which has been included two piers of RCC bridges with a length of 30 and 70 meters each, and some 119 numbers of culverts and ditches.

With the completion of this road project, several districts of Kapisa province will be connected with each other’s, and it will lead to huge positive changes in the agricultural, economic and social sectors.

MoPW Media Team – Kabul

1 year 3 months ago

.

تازه ترین اخبار

یکشنبه ۱۴۰۵/۹/۸ - ۱۰:۴۹
Background image

کار ترمیم و تحکیم کاری چهار پایه پل در ولایت ارزگان آغاز شد

کار ترمیم و تحکیم کاری چهار پایه پل (پل وانو، پل گرماب، پل سرخم در مرکز ترینکوت و پل منان در ولسوالی دهراود) از سوی وزارت فواید عامه ا.ا.ا، با سکتور خصوصی قرارداد و با حضور محترم الحاج. . .

شنبه ۱۴۰۵/۹/۷ - ۹:۱۷
Background image

کار ترمیم ۱۸ کیلومتر سرک ولسوالی قرغیی – درونته ولایت لغمان با ۴۰ درصد پیشرفت جریان دارد

کار ترمیم حدود ۱۸ کیلومتر سرک از مرکز ولسوالی قرغیی الی درونته ولایت لغمان، از سوی وزارت فواید عامه به ارزش ۱۷ میلیون افغانی با سکتور خصوصی قرارداد شده و در حال حاضر با سرعت جریان دارد.. . .

پنجشنبه ۱۴۰۵/۹/۵ - ۱۰:۸
Background image

کار اعمار یک بخش دیگری از شاهراه سالنگ‌ها در سالنگ جنوبی آغاز شد و وزیر محترم فواید عامه از جریان کار این شاهراه بازدید کرد

محترم الحاج ملا محمد عیسی ثانی، وزیر فواید عامه ا.ا.ا، به‌منظور ارزیابی کیفیت، میزان پیشرفت، سرعت کار و رعایت معیارهای تخنیکی، از جریان کار بخش‌های مختلف شاهراه سالنگ‌ها بازدید کرد.

وز. . .

BACK TO NEWS