Daikundi: The urban roads of Nili City reach 73% progress

Anonymous (not verified)
سه‌شنبه ۱۴۰۰/۵/۵ - ۱۳:۹
Daikundi: The urban roads of Nili City reach 73% progress

The 8.8 km long and 14 meters wide urban roads project in Nili city, the capital of Daikundi province, is underway and has reached 73% of physical progress, so far.

According to the Ministry of Public Works, the contract of this project was signed with a private construction company, which valued more than 631 million Afghanis and was funded by the Afghan government.

The implementation of this project was the main demand of the people of Daikundi province. With the completion of this project, in addition to reducing traffic congestion and air pollution inside the city; indeed, it will also reduce the transport costs and waste of time.

MoPW Media Team - Kabul

4 months 2 weeks ago

.

تازه ترین اخبار

شنبه ۱۴۰۴/۱۰/۲۰ - ۹:۳۲
Background image

کار ترمیم و داغگیری ۵۶.۳ کیلومتر سرک مزارشریف – دره صوف ۴۲ فیصد تکمیل شده است

به ‌منظور حل مشکلات رفت و آمد هموطنان گرامی ما در ولایت بلخ از سوی وزارت فواید عامه اـ.ا.-ا کار ترمیم و داغگیری سرک مزارشریف – دره‌ صوف به ارزش ۱۵۹ میلیون افغانی آغاز شده بود که هم. . .

پنجشنبه ۱۴۰۴/۱۰/۱۸ - ۸:۳۰
Background image

دیدار معینان وزارت فواید عامه ا.ا.ا با سفیر جمهوری اسلامی ایران

محترم الحاج مولوی عبدالکریم فاتح، معین تخنیکی وزارت فواید عامه ا.ا.ا در حضورداشت محترم الحاج ملا عبدالحق آخند، معین مالی و اداری این وزارت، با محترم علی‌رضا بیگدلی، سفیر جمهوری اسلامی. . .

دوشنبه ۱۴۰۴/۱۰/۱۵ - ۱۱:۳۴
Background image

در هفته گذشته از طریق خط آهن (۱۷۰۶۲۶) متریک تُن انتقالات صورت گرفته است

در هفته گذشته از تاریخ (۵  الی۱۱ جدی، سال ۱۴۰۴ هـ.ش.) از طریق خطوط آهن وزارت فوایدعامه افغانستان (۱۷۰۶۲۶) متریک تُن انتقالات صورت گرفته است.

در این میان از طریق بندر حیرتان (۱۱۳۳۵۱). . .

BACK TO NEWS