Bamyan: The Bridge and 300–meter road In Waras District, reaches 92% of progress

Anonymous (not verified)
شنبه ۱۴۰۰/۳/۱۵ - ۱۵:۲۴
Bamyan: The Bridge and 300 –meter road In Waras District, reaches 92% of progress

The project of a 15-meter-long RCC bridge, including a 300-meter long gravel road, located in Waras district of Bamyan province, reached 92 percent of physical progress.

According to the Ministry of Public Works, the project was funded by the Afghan government and has been contracted with the local development council of Ghajoor village for 10 million Afghanis.

Otherwise, this bridge’s project has been created around 730 working days for local workers and after the completion of this project, thousands of regional residents will be directly benefited.
 

MoPW Media Team - Kabul

6 months 4 weeks ago

.

تازه ترین اخبار

سه‌شنبه ۱۴۰۴/۱۲/۲۶ - ۹:۱۵
Background image

در هفته گذشته از طریق خط آهن وزارت فواید عامه 178421متریک تُن انتقالات صورت گرفته است

در هفته گذشته از تاریخ (۱۵  الی ۲۱حوت، سال ۱۴۰۴ هـ.ش.) از طریق خطوط آهن وزارت فوایدعامه افغانستان 178421 متریک تُن انتقالات صورت گرفته است.

در این میان از طریق بندر حیرتان 124533 تُن،. . .

پنجشنبه ۱۴۰۴/۱۲/۱۴ - ۱۲:۱۹
Background image

انتقالات از طریق چهار بنادر خط آهن کشور به‌گونه عادی جریان دارد

وزارت فواید عامه ا.ا.ا به هموطنان گرامی اطمینان می‌دهد که تا کنون هیچ‌گونه مانع در بخش انتقالات وجود ندارد و انتقالات از طریق چهار بندر خط آهن کشور به‌گونه عادی و منظم ادامه دارد.

در. . .

یکشنبه ۱۴۰۴/۱۲/۱۰ - ۱۲:۳۰
Background image

در مقایسه با ۱۱ ماه سال ۱۴۰۳ هـ.ش، انتقالات در ۱۱ ماه سال جاری بیش از ۳۳ درصد افزایش یافته است

از آغاز ماه حمل تا پایان ماه دلو سال ۱۴۰۴ هـ.ش، در مجموع (۵۳۸۷۵۴۹) متریک تُن انتقالات صورت گرفته است.

این در حالی است که در ۱۱ ماه سال گذشته (۱۴۰۳ هـ.ش) (۴۰۴۰۸۵۵) متریک تُن انتقالات. . .

BACK TO NEWS