The Bagram crossroad - Jabal Seraj road reaches 80% work progress

Anonymous (not verified)
دوشنبه ۱۴۰۰/۳/۳۱ - ۱۵:۴۸
The Bagram crossroad - Jabal Seraj road reaches 80% work progress

Parwan: The 2nd line road project that lay parallel to the Kabul-Parwan highway, which starts from the Bagram crossroad area and reaches the town of Jabal Seraj District, reached its 80% work progress, so far.

According to the Ministry of Public Works, this project has 25.6 km length and almost 10 meters width, included three piers of RCC Bridges and 106 piers of culverts piers along with other related structures.

The contract of this project was signed between the Ministry of Public Works and two private construction companies, was one of the priorities of the MoPW, which financially, was funded by the Afghan Government.

MoPW Media Team - Kabul

8 months 2 weeks ago

.

تازه ترین اخبار

شنبه ۱۴۰۵/۲/۱۹ - ۱۰:۵۵
Background image

پروژه اعمار و ساختمان لات اول سرک بلخ - شبرغان( سرک بندرکلفت) به طول ۲۵ کیلومتر در ولایت بلخ جریان دارد

پروژه اعمار و ساختمان لات اول سرک بلخ - شبرغان(سرک بندر کلفت) به طول ۲۵ کیلومتر و با هزینه بیش از ۷۵۲ میلیون افغانی میان وزارت فواید عامه و یکی از شرکت های سرکسازی به شکل دیزاین بلت. . .

چهارشنبه ۱۴۰۵/۲/۱۶ - ۱۳:۲۶
Background image

وزیر فواید عامه ا.ا.ا با سفیر جمهوری اسلامی ایران دیدار کرد

محترم الحاج ملا محمدعیسی ثانی، وزیر فواید عامه ا.ا.ا، با محترم علیرضا بیکدلی، سفیر جمهوری اسلامی ایران، در دفتر کاری‌اش در حالی که محترم الحاج مولوی عبدالکریم فاتح، معین تخنیکی وزارت. . .

چهارشنبه ۱۴۰۵/۲/۱۶ - ۱۱:۲۳
Background image

در هفته گذشته از طریق خط آهن ۲۲۹۵۳۶متریک تُن انتقالات صورت گرفته است

در هفته گذشته از تاریخ (۴ الی ۱۰ثور، سال ۱۴۰۵ هـ.ش.) از طریق خطوط آهن وزارت فوایدعامه افغانستان ۲۲۹۵۳۶متریک تُن انتقالات صورت گرفته است.

در این میان از طریق بندر حیرتان ۱۵۸۱۳۳ تُن،. . .

BACK TO NEWS