Construction of a road in 17th Nahia(region) of Kabul is 65 percent complete

This 1.8 km long asphalt road project that was recently inaugurated in Nejat Mina, one of the residential towns of the 17th district of Kabul city, has reached 65% work progress so far.. . .

Mon, Jun 28 2021 10:56 AM
Background image

A 10 km long road project has started in Narang district of Kunar

This concrete road project located in the Narang district of Kunar province has 10 km length and 4.8 meters width, which worth at least 100 million Afghanis that is being funded from. . .

Mon, Jun 28 2021 10:25 AM
Background image

Bamyan: The Naal Shera-Martyrs' Gate Road is ready for inauguration

The construction work of a 6-kilometer long gravel road, which starts from the Naal Shera area and reaches the martyrs’ gate of Bamyan, is completed and will be put into operation soon.. . .

Mon, Jun 28 2021 9:59 AM
Background image

Kandahar: Construction of a road in Daman district reaches 22% progress

This road project that extends from Taryaki Baba village of Daman district to the Kabul - Kandahar national highway, is a 4 kilometer long and 5 meters wide concrete road.

The project. . .

Sat, Jun 26 2021 4:02 PM
Background image

Maintenance of Gardez-Khost highway was accomplished

Paktia: As the Ministry of Public Works always strives to ensure that the road maintenance department is always active and recovering slight damages to prevent further destruction of. . .

Sat, Jun 26 2021 12:13 PM
Background image

Laghman: 2nd Lot of Mehtarlaam-Baadpakh Road reaches 56% Physical Progress

The official of MoPW/Laghman directorate says; the 2nd lot of the road between Mehtarlaam-Baadpakh is under construction, which is 21-kilometer-long and 6-meter-wide has achieved its 56. . .

Sat, Jun 26 2021 12:06 PM
Background image

1st section of the Kunar-Nuristan road is underway with 53% progress

Nuristan: Construction of the first part of the road between Kunar and Nuristan, which is 11 kilometers long and 8 meters wide, is underway and has reached 53 percent of work progress. . .

Sat, Jun 26 2021 11:28 AM
Background image

Yakawlang-Dara-e-Suf road is more than 58 percent complete

Bamyan: The road that extends from the Yakawlang district of Bamyan province to the Dara-e-Suf district of Samangan province is underway and has reached its 58 percent work progress so. . .

Thu, Jun 24 2021 3:16 PM
Background image

Jalalabad: The Abdulkhel to Behsud-Bridge beltway road project reaches 28% Work Progress

The 12-kilometer long and 40-meter wide road project starts from Behsud Bridge and continues to the provincial road of Kunar nearby Abdulkhel village, which is like a beltway in the. . .