Kandahar: Construction of a road in Daman district reaches 22% progress

Anonymous (not verified)
دوشنبه ۱۴۰۰/۴/۷ - ۹:۵۹
Kandahar: Construction of a road in Daman district reaches 22% progress

This road project that extends from Taryaki Baba village of Daman district to the Kabul - Kandahar national highway, is a 4 kilometer long and 5 meters wide concrete road.

The project has been contracted between the Ministry of Public Works and a private construction company, has 22 percent progress up to date, and was funded by the Afghan Government.

This road connects the villages of Taryaki Baba, Anaar Bagh, and Mohmand with the center of Daman district and the Kabul-Kandahar national highway

During the construction of this project, some 3157 working days of employment are predicted for the local residents.

Ministry of Public Works says, with the completion of this road project, the transportation problem of the entire villages will be totally solved, forever.

MoPW Media Team - Kabul

11 months 1 week ago

.

تازه ترین اخبار

پنجشنبه ۱۴۰۵/۵/۱۵ - ۱۰:۲۷
Background image

پروژه ترمیم پل چغه و پل آقتاش در ولایت کندز به ارزش بیش از ۱۲میلیون افغانی جریان دارد

پروژه ترمیم پل چغه بالای دریای بنگی به طول ۸۴متر و عرض ۱۰متر و ترمیم پل آقتاش به  طول ۱۰۰متر و عرض ۸.۴متر در ولایت کندز، به ارزش ۱۲میلیون و ۵۰ هزار افغانی از سوی وزارت فواید عامه با. . .

چهارشنبه ۱۴۰۵/۵/۱۴ - ۱۳:۵۹
Background image

پروژه اعمار لات سوم سرک حلقوی قیصار – لامان به طول ۵۰ کیلومتر به ارزش بیش از ۴.۶میلیارد افغانی جریان دارد

پروژه اعمار لات سوم سرک حلقوی قیصار – لامان در ولایت بادغیس به طول ۵۰کیلومتر و عرض ۱۲متر، به ارزش ۴میلیارد و ۶۵۲ میلیون و ۵۳۶هزار افغانی از سوی وزارت فوایدعامه ا.ا.ا با سکتور خصوصی. . .

سه‌شنبه ۱۴۰۵/۵/۱۳ - ۱۴:۵۰
Background image

کار قیرریزی لات اول سرک میدان وردک – بامیان جریان دارد

پروژه بازسازی اساسی ۲۵ کیلومتر لات اول شاهراه میدان وردک – بامیان به ارزش بیش از ۸۵۸ میلیون و ۴۵۰ هزار افغانی، از سوی وزارت فواید عامه ا.ا.ا با یک شرکت خصوصی قرارداد شده است و درحال. . .

BACK TO NEWS