The Dara-e-Suf district - Shabashk mine in under rapid construction

Anonymous (not verified)
چهارشنبه ۱۴۰۰/۴/۹ - ۹:۵۱
The Dara-e-Suf district - Shabashk mine in under rapid construction

Samangan: This road starts from the Bazar-e-Sukhta of Dara-e-Suf district and ends in the beginning part of the Shabashk mine of Samangan province, has 37.194 kilometers length and 10 meters width.

According to the Ministry of Public Works, this project has included two bridges with a total length of 80 meters, 112 culverts of different sizes, and 56 causeways with a total length of 6400 meters.

This project is contracted between the Ministry of Public Works and a private construction company and funded by the Government of Afghanistan.

MoPW Media Team-Kabul

1 year 2 months ago

.

تازه ترین اخبار

پنجشنبه ۱۴۰۵/۸/۱۴ - ۱۰:۷
Background image

افزایش بیش از دو برابر انتقالات اموال تجارتی از طریق راه آهن در شش ماه نخست سال ۱۴۰۵ هـ.ش.

در شش ماه نخست سال ۱۴۰۵ هـ.ش، از طریق چهار مسیر تجارتی شامل بندر حیرتان، بندر آقینه، بندر تورغندی و مسیر خواف–هرات، مجموعاً ۴ میلیون و ۸۸۸ هزار و ۲۶۸ متریک تُن اموال تجارتی انتقال یافته. . .

چهارشنبه ۱۴۰۵/۸/۱۳ - ۱۵:۱۶
Background image

کار ترمیم و بازسازی دو پایه‌ پلچک در مسیر سرک ولسوالی چارکنت ولایت بلخ به ارزش بیش از ۴.۴ میلیون افغانی آغاز شد

کار ترمیم دو پایه‌ پلچک در مسیر سرک ولسوالی چارکنت ولایت بلخ، به ارزش بیش از ۴.۴ میلیون افغانی، از سوی وزارت فواید عامه ا.ا.ا و با حضور محترم مولوی عبدالصبور صابر، رئیس فواید عامه ولایت. . .

دوشنبه ۱۴۰۵/۸/۱۱ - ۱۰:۴۴
Background image

کار ترمیم و بازسازی سرک مرکز شرنه – ارگون در ولایت پکتیکا آغاز شد

کار ترمیم و بازسازی سرک  مرکز شرنه - ارگون ولایت پکتیکا از منطقه پی‌آر‌تی الی پیرکوتی  به طول ۵۰ کیلومتر از سوی وزارت فوایدعامه ا.ا.ا، به ارزش ۲۵ میلیون و ۳۰۱ هزار افغانی با سکتور خصوصی. . .

BACK TO NEWS