Daikundi: The urban roads of Nili City reach 73% progress

The 8.8 km long and 14 meters wide urban roads project in Nili city, the capital of Daikundi province, is underway and has reached 73% of physical progress, so far.

According to the Ministry of Public Works, the contract of this project was signed with a private construction company, which valued more than 631 million Afghanis and was funded by the Afghan government.

The implementation of this project was the main demand of the people of Daikundi province. With the completion of this project, in addition to reducing traffic congestion and air pollution inside the city; indeed, it will also reduce the transport costs and waste of time.

MoPW Media Team - Kabul

...

۱ کال 2 میاشتې ago

...

تازه خبرونه

پنجشنبه ۱۴۰۵/۸/۲۱ - ۱۱:۱۳
Background image

د کندز – شېرخان بندر سړک د ترمیم چارې د څه باندې ۲۰.۴ میلیونه افغانیو په ارزښت پیل شوې

د ا.ا.ا د ټولګټو وزارت له لوري د کندز ولایت اړوند د کندز – شېرخان بندر عمومي سړک د ترمیم چارې د څه باندې ۲۰.۴ میلیونه افغانیو په ارزښت له خصوصي سکتور سره قرارداد شوې دي، چې د کندز ولایت. . .

شنبه ۱۴۰۵/۸/۱۶ - ۱۵:۱۲
Background image

د ټولګټو وزارت محترم وزیر په کاپیسا ولایت کې د یو شمېر پروژو له کاري بهیر څخه لیدنه او ارزونه وکړه

د ا.ا.ا د ټولګټو وزارت محترم وزیر الحاج ملا محمد عیسی ثاني د ترانسپورتي زیربناوو د پراختیا، د سړکونو د رغنیزو چارو د کیفیت او چټکتیا د ډاډ ترلاسه کولو او د پروژو د کاري بهیر د ارزونې په. . .

پنجشنبه ۱۴۰۵/۸/۱۴ - ۱۰:۴
Background image

د ۱۴۰۵ هـ.ش کال په لومړیو شپږو میاشتو کې د اوسپنیزې لارې څخه د سوداګریزو توکو انتقالات څه باندې دوه برابره زیات شوي دي

د ۱۴۰۵ هـ.ش کال په لومړیو شپږو میاشتو کې د حیرتان، آقینې او تورغونډۍ بندرونو او د خواف ـ هرات د اوسپنیزې لارې له مسیر څخه په ټولیزه توګه ۴ میلیونه او ۸۸۸ زره او ۲۶۸ مټریک ټنه سوداګریز. . .

BACK TO NEWS