Bamyan: The Naal Shera-Martyrs' Gate Road is ready for inauguration

ناپیژنده (not verified)
دوشنبه ۱۴۰۰/۴/۷ - ۱۰:۲۵
Bamyan: The Naal Shera-Martyrs' Gate Road is ready to be inaugurated

The construction work of a 6-kilometer long gravel road, which starts from the Naal Shera area and reaches the martyrs’ gate of Bamyan, is completed and will be put into operation soon.

The project has included two sections that was been contracted with two village development councils.

According to the National Road Access Program (NRAP), this project connects the villages of Ledo, Darvazaha, Naal Shera, and the Martyrs' gate with the capital of Bamyan.

During the construction period, this project brought some 15,659 working days for the local people.

With the completion of this project, the transportation problems of the residents will be solved and they will be able to transfer their agricultural products to the local marketplace safe and on time.

MoPW Media Team - Kabul

...

3 میاشتې 3 اونی ago

...

تازه خبرونه

سه‌شنبه ۱۴۰۴/۹/۲۵ - ۱۳:۵۷
Background image

ټولګټو وزارت د سړکونو د ساتنې او څارنې مرستیال د هېواد ختیځ زون ته سفر وکړ

د ا.ا.ا د ټولګټو وزارت د سړکونو د ساتنې او څارنې مرستیال، محترم الحاج معاون ملا عبدالجبار، د یو تخنیکي او مسلکي پلاوي په ملتیا د ټولګټو وزارت د روانو رغنیزو او زیربنایي پروژو د ارزونې،. . .

دوشنبه ۱۴۰۴/۹/۲۴ - ۱۵:۶
Background image

په تېره اوونۍ کې د اوسپنې پټلۍ له لارې (۱۶۳۴۳۷) مټریک ټنه انتقالات شوي دي

په تېره  اوونۍ کې (د ۱۴۰۴ هـ.ش. کال قوس له ۱۴مې څخه د قوس تر ۲۰مې) نېټې پورې د ټولګټو وزارت د اوسپنې پټلۍ له لارې (۱۶۳۴۳۷) مټریک ټنه انتقالات شوي دي.

د حیرتان بندر له لارې (۱۱۷۲۱۳) ټنه. . .

یکشنبه ۱۴۰۴/۹/۲۳ - ۱۳:۲۱
Background image

په پنجشیر ولایت کې د ۶.۳ میلیونه افغانیو په ارزښت د دوو پایو پلونو د ترمیم او بیا رغونې چارې بشپړې شوې

د ا.ا.ا د ټولګټو وزارت لخوا د پنجشیر ولایت د رخه ولسوالۍ د قابضان او د پریان ولسوالۍ د مرغابي‌ دان پلونو د ترمیم او بیا رغونې چارې د ۶.۳ میلیونه افغانیو په ارزښت بشپړې او ګټې اخیستنې ته. . .

BACK TO NEWS